Pembina Trails Collegiate

This new 117,000 square foot high school is planned around a large two storey Student Commons that connects the bus loop on the east side to the student and staff parking on the west. The design includes an MPR/Gym/Fitness suite, and Canteen, that are all connected to additional leaning spaces. The school also features a stair that serves all three storeys of the classroom wing.  The 4000 square foot fully glazed, two storey Library opens on to an exterior landscaped courtyard.

Pembina Trails Collegiate has been designed for 1000 students. The school is currently under construction and is expected to open in 2023.

PTC%202.jpg


Location
50 Frontier Trail, Waverley West
Prime Consultant
LM Architectural Group
Contractor
Penn-Co Construction
Cost
$37.6 Million

 PTC%203.jpg

Ecole RHG Bonnycastle Elevator Addition and Entrance Renewal

The project scope includes an elevator addition, a barrier free washroom and new entrances at both east and west locations. Upgrades within the school which will accommodate barrier free access to two floors. Work will include architectural, structural, mechanical, and electrical components.

The project is expected to be completed by the fall of 2023.

Bonnycastle%201.jpg


Location
1100 Chancellor Drive
Prime Consultant
Prairie Architects Inc.
Contractor
Marrbeck Construction
Cost
$2.1 Million
Bonnycastle%203.jpg
Bonnycastle%202.jpg

École St. Avila Elevator Addition

The project scope incudes an elevator addition and barrier free washroom upgrades within the school which will accommodate barrier free access to two floors. Work will include architectural, structural, mechanical, and electrical components.

The project is expected to be completed in early 2023. 

St%20Avila%201.png


Location
633 Patricia Ave
Prime Consultant
Prairie Architects Inc.
Contractor
Tractus Projects
Cost
$1.4 Million

St%20Avila%20plans.jpg